The following principles shall be followed during the installation of rebar mesh welding machine:
1. The rebar mesh welding machine must be placed stably in a well ventilated and dry place, and it is not allowed to be close to the dangerous environment of high heat, flammability and explosion.
2. The steel formwork rebar mesh welding machine shall be protected from collision or severe vibration (especially arc welding rectifier). The rebar mesh welding machine used outdoors must be protected from rain and snow.
3. The steel formwork rebar mesh welding machine must have a special independent power switch, and its capacity shall meet the requirements. When the welding machine is overloaded, it shall be able to cut off the power automatically. It is forbidden to share one power switch for multiple welding machines.
4. The power control device shall be installed near the welding machine where it is convenient for manual operation, and there shall be a safe passage around.
5. The length of the primary power line of the rebar mesh welding machine should not exceed 2-3m in general. When a long power line is needed for a temporary task, it shall be separated and arranged along the wall or column with porcelain bottle, and its height must be more than 2.5jn from the ground, and it is not allowed to drag the power line on the ground.
6.The live part of the rebar mesh welding machine shall be equipped with intact protection (isolation) device. The exposed terminal of the rebar welding machine must be equipped with a welding machine connected by a protective plug and socket. The terminal of the pin hole shall be isolated by an insulating partition and installed in the plane of the insulating board.
7. The shell of the steel formwork welding machine must be grounded, and the grounding device must always be well connected. It is forbidden to use flammable and explosive gas pipes such as oxygen pipes and acetylene pipes as the natural grounding electrodes of the grounding device, so as to prevent sparks from detonating due to the effect of resistance heat or arc striking current.
8. When the steel formwork welding machine is connected to the power grid, the voltage of the two must be the same.
9. After the arc welding generator is connected to the power grid, start the test run first, and observe whether the rotation direction of the commutator is consistent with that specified on the welding machine. If it is the opposite, replace the position of any two phases in the three-phase power line.
10. the wiring and installation of the welding machine shall be in the charge of a special electrician, and the welder shall not do it just by himself.
September 4, 20191. Relief method for the failure of the wire straightening and cutting machine starting up normallyWhen the machine has a fault that can only be jogged and cannot be started normally, check the contro...view
April 22, 2019Along with the increasing use of steel bars in the construction industry, there are more and more stirrup processing equipments springing up in the industry.view
February 22, 2021The bar cutting machine is designed to cut all kinds of round rebar and deformed rebar to a fixed length. It is a typical rebar cutting processing equipment. Generally, there are two types of automati...view
October 1, 2018Any rebar machine equipment has its own characteristics, rebar bending machine is no exception. Its characteristics directly related to the equipment in the actual use of the situation, so customers i...view
August 17, 2019The wire straightener itself has several special properties. Here, the author takes the reinforcing wire material as an example to introduce these few properties for everyone to understand.First of al...view
February 25, 2020I.shear installation and test run of rebar shear1.Rebar shear machine shall be installed on flat and solid ground.2. When installing the bearing frame, the center of the bearing frame material groove ...view