Stirrup Bending Machine operating procedures and precautions:

1. Check whether the mechanical performance is good, the worktable and the bending machine table should be kept level; and prepare various mandrel tool blocks.

Second, according to the diameter of the processed steel bar and the requirements of the hoop machine, the core shaft, the forming shaft, the iron blocking shaft or the variable blocking frame are installed.

3. The steel bending hoop machine checks the mandrel, the stopper and the turntable should be free of damage and cracks, the protective cover should be fastened reliably, and the normal operation can only be confirmed after the empty machine is running.

4. During operation, insert the bent end of the steel bar into the gap provided by the turntable, and fix the other end against the fuselage and press it by hand. Check the fixation of the fuselage and ensure that it is installed on the side blocking the steel bar before it can be started.

5. During Stirrup Bending Machine operation, it is strictly forbidden to replace the mandrel, change the angle, adjust the speed and other operations, nor add oil or remove it.

6. When bending steel bars, it is strictly forbidden to process the diameter, number and speed of the steel bars that exceed the mechanical requirements.

7. When bending high-hardness or low-alloy steel bars, Stirrup Bending Machine should change the standard-restricted diameter according to the mechanical nameplate, and replace the corresponding mandrel.

8. Stirrup Bending Machine is strictly forbidden to stand on the side of the bending steel bar and the side where the fuselage is not fixed. The bent semi-finished products should be stacked neatly, with the hooks not facing upward.

9. When the turntable changes direction, it must be carried out after stopping.

Ten. The operation of the steel bending hoop machine is completed, the site is cleaned, the machinery is maintained, and the lock box is cut off